The PMP MCQ questions with answers section is ideal for candidates aiming to earn Project Management Professional (PMP) certification or succeed in related job interviews. These programming questions and answers focus on project planning, risk management, stakeholder communication, and agile methodologies. By practicing these MCQs, you enhance your understanding of real-world project scenarios and PMI standards. Each question includes clear explanations aligned with the PMBOK guide to ensure conceptual clarity. This resource is valuable for both beginners and professionals preparing for PMP, CAPM, or technical project management roles.

PMP MCQ

Showing 10 of 406 questions

201. Which of the following statement are false regarding issue logs?

  • Issue logs are written logs that document person responsible for resolving for specific issue by a target date
  • Issue logs are tool of manage stakeholders process
  • Issue logs are tool of manage project team process
  • Issue logs describes the ground rules and conflict management procedures to manage the project
Show Answer Report

202. Your company is making a strategy shift: form being focused on fulfilling customer requests for becoming the best cost dairy producer in industry. Its existing cost manufacturing cost system, however fails to capture the costs associated with handling special flavors, small production orders, and complex delivery and order processing options. Hence you

  • Your ability to yield adequate authority to make resource allocation decisions regarding the project
  • The difficulty in determining who will serve on the change control board due to the number of stake holders.
  • The overhead that is required to notify the large number of stakeholders regarding changes that affect the project
  • The amount of time that will be spent on configuration management due to the number of stake holders
Show Answer Report

203. Product analysis uses which of the following techniques EXCEPT:

  • Value analysis
  • Inspection
  • Product break down
  • Systems engineering
Show Answer Report

204. A poorly defined staffing management plan will LEAST impact:

  • Human resource planning
  • Acquire project team
  • Manage project team
  • Cost estimating
Show Answer Report

205. You are the project manager responsible for constructing new 100-unit apartment in downtown Manhattan. As part of construction project, you are planning to outsource the electrical wiring of the building to an outside contracting firm. The contracting firm has requested a statement of work from you. Which of the following statements are FALSE regarding the contract SOW?

  • The SOW contains the objectives of the project
  • As a buyer, you re required to write SOW
  • The SOW is an output of the and acquisitions process and an input to the plan contracting process
  • The outside contracting firm requires a SOW to determine they have the capabilities to meet the detailed specifications of the project
Show Answer Report

206. Activity cost estimates and its supporting details are output of which process?

  • Activity duration estimation
  • Cost control
  • Cost estimating
  • Activity resource estimating
Show Answer Report

207. Which of the following best describes the amount of time one can delay the start of a task without delaying the start of a successor task?

  • Lag time
  • Lead time
  • None of the choices are correct
  • Free slack
Show Answer Report

208. You

  • Analogous estimation
  • Quantitatively based durations
  • Decomposition
  • Expert judgment
Show Answer Report

209. A risk management plan is a subset of the project management plan and describes how risk management should be performed. All of the following should be included in the risk management plan EXCEPT:

  • None of the choices are correct
  • Budgeting, timing, risk categories
  • Methodology, roles and responsibilities
  • P-l matrix, tracking
Show Answer Report

210. You are using the three-point estimating technique to estimate the duration of a schedule activity. Which of the following is the correct formula for calculating variance assuming a triangular distribution?

  • [(optimistic-pessimistic)^2+(most likely pessimistic)*(most likely-optimistic)]/18
  • ((optimistic-pessimistic)/6)^2
  • (pessimistic + optimistic + most likely )/3
  • (pessimistic +4 *(most likely)+ optimistic)/6
Show Answer Report